Abuja's Apo-Karshi road completed after years of delay: what Wike said about its opening and plans for the corridor
FCT Minister Nyesom Wike inspected the completed Apo-Karshi road in Abuja on Wednesday 11 November and said the corridor will be developed into a tourist attraction. The road was first awarded in 2010 but stalled for years. Wike said he hopes President Bola Tinubu will formally commission it before the end of November, depending on the President's schedule.
Background: The 13-kilometre road was originally given to Kakatar Engineering Limited for N6.4 billion, with 20 months to finish, BusinessDay reported. In November 2025 the FCT Administration terminated that contract and re-awarded it to SCC Nigeria Limited under emergency procurement. Wike said at the time that the road would give residents of Nyanya and Karu an alternative route to the city centre.
At Wednesday's inspection, Wike said the first contractor had been fully paid but did not deliver, and that Tinubu directed that the contract be terminated and re-awarded, Vanguard, Daily Trust and Leadership reported. He said the administration was not deterred by criticism of the cost of the new contract, whose value was not stated in the reports. He said the road agency should stick to road work, while the department responsible for tourism would decide what facilities to build along the route. He added that 10 to 12 other FCT projects were also being lined up for commissioning.
Pidgin: FCT Minister Wike inspect di Apo-Karshi road for Abuja on Wednesday 11 November and talk say dem go turn di corridor to tourist centre. Dem first award di road for 2010 but e stand for many years until dem give am to SCC for November 2025. Wike hope say President Tinubu go commission am before November end.
How this affects you: If you live in Karu, Nyanya, Karshi or nearby satellite towns, the road is meant to give you another way into the city that avoids the crowded Nyanya corridor. It has not yet been formally commissioned and no date has been fixed, so watch for FCT announcements on the official opening and any traffic arrangements on that day. The tourist facilities are only at the planning stage: no design, cost or timeline has been announced.